Refurbishment Progress story (wks 8-9). refurbishment supported by
.......... ONYX ......... &..........


return to homepage

day 45 - (10Mar)

- kitchen/bar flooring going down

- prep for ceiling to be installed over the w/e

- lobby heater now in

- toilet basically complete

- all doors basically complete

- hatch doors still to be painted to 'blend' into hall wall colouring

- various minor finishing off building work (for snagging and later completion)

......

from the meeting room side..see below..
......

LAST WEEK...

day 39 - (2Mar)

- lobby / entrance / toilet - floor coverings down.

- Kitchen/bar partition underway.

- lobby doors awaiting glazing & handles

- new entrance safety rail

- general decoration

.... .... ...