Refurbishment Progress story (wks 8-9).
refurbishment supported by |
return to homepage
day 45 - (10Mar)- kitchen/bar flooring going down- prep for ceiling to be installed over the w/e- lobby heater now in- toilet basically complete- all doors basically complete- hatch doors still to be painted to 'blend' into hall wall colouring- various minor finishing off building work (for snagging and later completion)...... from the meeting room side..see below..
LAST WEEK...
day 39 - (2Mar)- lobby / entrance / toilet - floor coverings down.- Kitchen/bar partition underway.- lobby doors awaiting glazing & handles- new entrance safety rail- general decoration.... .... ... record ...going back in time...
see weeks 5,6,7
see fourth week
see third week
see second week
see first week & preparation
|