Refurbishment Progress story (3rd week)..
supported by |
day 14 (26 Jan)- Final detail design drawings from CHR now approved. DBK work on drains and new kitchen door and ramp to new side entrance
day 13- plastering completed & drains nearly complete. DBK nearly ready for CHR to kit-out the kitchen/bar with floor/ceiling/bar/kitchen units............. one more drain gulley to go
day 12 - plastering & drains............ ...... trench for ramp to new entrance.
end of day 11 - toilet room and outer entrance lobby part plastered - ironmongery into new exterior entrance door - gas pipe rerouted - new drain inspection chamber. Final drawings for kitchen/bar now completed/approved to start manufacture