front of the building with some users   

Refurbishment Progress story (3rd week).. supported by
.......... ONYX ......... &..........


day 14 (26 Jan)- Final detail design drawings from CHR now approved. DBK work on drains and new kitchen door and ramp to new side entrance

day 13- plastering completed & drains nearly complete. DBK nearly ready for CHR to kit-out the kitchen/bar with floor/ceiling/bar/kitchen units.

............ one more drain gulley to go

day 12 - plastering & drains

............ ...... trench for ramp to new entrance.

end of day 11 - toilet room and outer entrance lobby part plastered - ironmongery into new exterior entrance door - gas pipe rerouted - new drain inspection chamber. Final drawings for kitchen/bar now completed/approved to start manufacture

see second week

see first week & preparation

return to homepage