Refurbishment - Progress story (2nd week) -
...supported by |
end of 2nd week - new side entrance door cut and installed - boarded off from outside. - progress on toilet enclosure. see also first week & preparation......
end of day 9 - new drains partly installed. Most walls ready for plasterer next week.
end of day 8 - old kitchen & lobby/bowls store floors now removed - excavation of drains incl . inside for new toilet. Kitchen hatches & double-door from main hall now sealed to hopefully reduce building dust ingress.photo of external drains doesn't show much but included for completeness
end of day 7 |