front of the building with some users   

Refurbishment - Progress story (2nd week) - ...supported by
.......... ONYX ......... &..........


end of 2nd week - new side entrance door cut and installed - boarded off from outside. - progress on toilet enclosure. see also first week & preparation

......

end of day 9 - new drains partly installed. Most walls ready for plasterer next week.

end of day 8 - old kitchen & lobby/bowls store floors now removed - excavation of drains incl . inside for new toilet. Kitchen hatches & double-door from main hall now sealed to hopefully reduce building dust ingress.

photo of external drains doesn't show much but included for completeness

end of day 7
- most of old kitchen floor now removed - drain excavated for gaspipe.

......

TRANSCO will be rerouting gaspipe and repairing drain (this problem was identified when we had the drains videocamera'd as part of the 'Condition' survey)

end of day 6 - hatches into main hall( 'blanked off' until doors fitted) - good proportion of floor now removed.

......

see first week & preparation